These are the meeting notes I took so sorry if they are a little scrappy but here is an update on busway fencing.

Orchard Crossing, Histon

The full northern busway stretch has gone out to procurement. 5 tenders have come back which is everyone who’s on the procurement framework.   The busway team are evaluating and moderating the tenders.   Hoping to award the contract by 1 Dec then start work on the fencing at the start of Jan.

In terms of the crossing once procurement is complete the programme will be worked out with phasing and diversions.  We’re a couple of weeks away from knowing who is successful.– ‘but it looks really positive’ [officer comment]. December will be really busy organising this.

Orchard Park spur – the guided section will have more solid fencing (P3) like Pagram Way to Histon.  This cannot be avoided for Health and Safety reasons.

Along the rest of Orchard Park the council are working closely with an independent HS advisor.   The stretch is largely unguided and 20mph.  There was a focus on blocking off crossing points.  But there’s a question over whether this is still the right approach or would it be better to continually fence the stretch with mesh fencing – still undecided as if you block certain sections off people will move along and break through other sections. The Orchard Park spur is phased for after Christmas so need to make a decision soon but it’s really hard as it’s a complex situation. Feels more like a road in nature but it’s under the same legislation as the rest of the busway.  [officers] Really thinking long and hard about this, looked at desire points, key risks etc and have worked closely with health and safety advisor.    Will come to speak to Orchard Park residents whichever way the decision goes.

Orchard Park Crossing – I raised the issue of visibility and sight lines. Some work has been done on this and a crossing near Addenbrookes and panels will be replaced to improve visibility and sight lines.

Lighting – now have a contract with M group every 28 days they are checking lights that are out, the entire length of the busway plus park and ride sights. Just had report from last lighting scout. More preventative works.   I [Ros] pushed to see the details on Gatehouse Road as a very large number of lights are out.  I will continue to push on this.  There are also some lights out at the His/Imp station.

Flooding – I raised the issue of the significant flooding where the busway meets Kings Hedges Road.  They will take a look.

We discussed the CRC crossing and compared it to Milton Road.  The active travel team [a separate team] are working on this but the proximity of a major gas station (might be wrong terminology) makes any work there really challenging and cadent have serious reservations.  I pointed out that the Science Park are coming to planning on 18 Nov and if their Science Park upgrade is accepted there will be a new entrance there so it might be possible to fund significant reworking of the entrance.

Although it seems as though everything has gone quiet it will start moving very fast in the new year